The Scrum Sprint Burndown Chart – Every Picture Tells a Story


#1 Football Merchandise & Souvenirs Store

We use Agile software developments methods and, for project management, Scrum is our preferred method. Our development team are based offshore and there are challenges to making Agile work with a distributed team but it can be done (and can be fun also!). So I thought I would share a story with you one of our real Sprints as told through the Scrum Burndown chart. Why? Well, because I think we can learn a great deal from the Burndown chart and everyone has its own story to tell. Here’s ours:

To set the scene, my Scrum team met (virtually of course) to plan the next iteration of our work developing a bespoke sales order processing system for a major UK utilities company. We knew which user stories the client Product Owner wanted in this Sprint and so we sat down, listed the tasks needed to build the user stories and estimated in hours how long each one would take. This initial estimate came out at 90 hours.

Having already been through a few Sprints, we had a good idea of the team’s velocity and reported to the Product Owner that this was too much to complete within the normal 2 week iteration. However, given the importance of this functionality to the client, and to maintain momentum leading up to the Christmas period, it was exceptionally agreed to run this Sprint for longer than normal.

All started well and good progress was made, in fact we were ahead of schedule. Then, a few days in, one of the team realised that a further task was needed to complete one of the user stories – so this was documented, estimated and added to the Sprint Backlog. This increased the estimated hours remaining by a further 16 hours and so the Burndown chart tracked north.

Within a couple of days, another unexpected incident occurred. The British Government announced a decrease in the VAT rate (sales tax) and, as the system we have built for our client is a sales order processing system, which includes pricing & invoicing calculations, we knew that this statutory change would need to be tackled as a matter of priority. Now, we’re a small team (what Agile team isn’t) and we quickly realised that all current development work would need to be suspended to make this critical change.

So we parked this Sprint and worked through the week and the weekend to successfully deliver the VAT change ready for the implementation date a week after the Government announcement. As a result, our Burndown chart flat-lined for a week. We therefore realised that this would impact on our estimated delivery date and so started to look at a revised completion window for this Sprint.

However, before we could complete this, the next hurdle appeared in front of us. The developer who had picked up a new task realised that it was more complex than we had originally estimated; as a result the effort remaining increased by a further 36 hours, leading to another upward spike on our chart and, of course, further delay in delivering this Sprint. So, again, based on the team’s velocity, we re-estimated and come out with a revised completion window.

Now, I can already hear some of you Scrum experts out there shouting at me. Surely we should have time-boxed the iteration and not extended it? When we dropped in the new task we should have possibly looked to the Product Owner to remove something in compensation in order to deliver within the Sprint? And all this is true – in an ideal Scrum world that’s what we would do. But, we know our client well, we have an excellent relationship with them, and we knew how important it was to them to get this functionality in before the New Year. So I bent the Scrum rules to accommodate their needs. Now, before I’m drummed out of the Scrum gang, we shouldn’t lose sight of the Scrum values:

* Be willing to commit to a goal.

* Do your job. Focus all of your efforts and skills on doing the work that you’ve committed to doing.

* Don’t worry about anything else.

* Scrum keeps everything about a project visible to everyone.

* Have the courage to commit, to act, to be open, and to expect respect.

Now, I’ll accept that we bent the Iteration rules a little, but it was for good reasons. We faced some unexpected change during the Sprint. But we were open and honest with the client and we were able to use the Sprint Burndown chart to quickly show the Product Owner the impact of change and gain their approval to proceed.

More importantly, we stayed in control and retained order in what could have been chaos.


#1 Football Merchandise & Souvenirs Store
Liverpool
Chelsea
Manchester City
Arsenal
Tottenham Hotspur
Manchester United
Leicester City
Newcastle United
West Ham United
Barcelona
Real Madrid

Source by Paul P Jackson
Arsenal Souvenir
Arsenal Souvenirs
Arsenal Merchandise
Arsenal Mugs
Arsenal Wallcoverings & Lighting
Arsenal Badges
Arsenal Pictures
Arsenal Drinks Bottles
Arsenal Current Players
Arsenal Gaming & Audio
Arsenal Footballs
Arsenal Toys & Games
Arsenal Silver Plated
Arsenal Gold Plated
Arsenal Socks
Arsenal Travel Mugs
Arsenal Gift Sets
Arsenal Kitchen
Arsenal Pennants
Arsenal Memorabilia
Arsenal Club Flags
Arsenal Scarves
Arsenal Toiletries
Arsenal Caps
Arsenal Backpacks & Holdalls
Arsenal Wallets
Arsenal Boot Bags & Gym Bags
Arsenal Knitted Hats
Arsenal Luggage Accessories
Arsenal Pet Accessories
Arsenal Keyrings
Arsenal Decorations
Arsenal Posters
Arsenal Annuals
Arsenal Lunch Bags
Arsenal UEFA Euro 2020
Arsenal Gloves & Shin Pads
Arsenal ArmBands & Sock Ties
Arsenal Mini Balls
Arsenal Cufflinks & Key Rings
Arsenal Hard Cases
Arsenal Calendars
Arsenal Glassware
Arsenal Diaries
Arsenal Gloves
Arsenal Doormats
Arsenal Stationery
Arsenal Bathroom
Arsenal Bedding
Arsenal Clocks
Arsenal Bracelets & Earrings
Arsenal Metal Signs
Arsenal Dog Tags & Pendants
Arsenal Clothing
Arsenal Cards & Gift Wrap
Arsenal Shirts
Arsenal Rings
Arsenal Pumps & Sets
Arsenal Wristbands
Arsenal Balls Tees & Towels
Arsenal Headcovers
Arsenal Leather
Arsenal Stickers
Arsenal Hang Ups
Arsenal Face Coverings
Arsenal T-Shirts / Polos
Arsenal Card Holder & Pens
Arsenal Miscellaneous
Arsenal Hip Flasks & Tankards
Arsenal Coasters
Arsenal Stationery Sets
Arsenal 9ct Gold
Arsenal Sterling Silver
Arsenal Bears & Soft Toys
Arsenal Rugs & Cushions
Arsenal Flip Flops
Arsenal Money Banks
Arsenal Watches
Arsenal Jackets
Arsenal Keys & Padlocks
Arsenal Limited Stock & Collectables
Arsenal Shorts
Arsenal National Flags
Arsenal National
Arsenal Masks
Arsenal Prints
Arsenal Gloves & Boots
Arsenal Accessories
Arsenal Brushes & Card Holders
Arsenal Golf Sets
Arsenal Soft Toys
Arsenal Hats & Stockings
Arsenal Mules
Arsenal Ties
Arsenal Sweats / Tracksuits
Arsenal Skins
Arsenal Umbrellas
Arsenal Gloves & Grips
Arsenal NFL
Arsenal Silicone
Arsenal Divot Tools & Markers
Arsenal Gift Bags & Wrap
Arsenal NBA
Arsenal Air Fresheners
Arsenal Hosting Solutions
Arsenal Moccasins
Arsenal Glasses Cases
Arsenal Inflatables
Arsenal England F.A.
Arsenal Shock Doctor
Arsenal Folios & Pouches
Arsenal Baby Booties
Arsenal Footwear
Arsenal Super Titanium
Arsenal Car Stickers